约翰·罗杰斯
约翰罗杰斯小学 Replacement Project
约翰罗杰斯小学 has moved to the interim site at John Marshall School, 东拉文纳大道520号, for the 2023-24 and 2024-25 school years.
时间轴
- 预设计阶段完成
- 方案设计阶段完成
- Design development phase complete
- Construction documents and permitting phase complete
- 投标和授予阶段完成
- 施工正在进行中
- 学校于2025年秋季开学
项目简介
The existing school building will be demolished, and a new school building will be constructed. Site work will terrace the site and seamlessly connect the 玩 field to the rest of the campus.
Designed for current and future students
The proposed design replaces the existing 约翰罗杰斯小学 with a new, 82,000 square foot 2- and 3-story building. 一旦完成, the school will provide an equitable learning space for up to 500 K-5 elementary students and an area to expand the school in the future as enrollment grows.
Thanks to the work of the School Design Advisory Team (SDAT) — comprised of school leaders, 父母, and community members — it will meet district educational standards for 500 students while also fulfilling the specific needs the specific needs of the 约翰罗杰斯小学 community.
The school will nestle into a newly terraced site that will enhance connections to nature, 玩, 户外学习. Campus improvements will provide a safe site for all. A new network of pathways and street access will connect the neighborhood to the school.
Outdoor learning areas will be improved, including a new natural turf field and drainage system. Natural 玩 areas will connect students to the site.
安全与保障
Visitors will enter through a secure main entrance that invites you into the administrative office for check-in before entering the school. All other doors will be locked during the school day.
Building for a sustainable future
The new 约翰·罗杰斯 小学 is being designed as 正规买足球的App’ first Net-Zero Energy building, ,包括:
- 一天light in all classrooms and learning spaces
- Highly efficient heating and fresh air ventilation
- Geothermal wells to use energy from the ground for heating and cooling
- Solar panels to use energy from the sun
项目进展
实时视频馈送
照片
建设更新
Project updates are posted for the previous month the week after the monthly BEX and BTA Capital Levies Oversight Committee meetings.
2024年3月
钢结构继续上升. Installation of glue-laminated (glulam) and steel decking started, which means that the first step for floors and ceilings can be seen. Work continues on the concrete block wall along the west side, concrete pouring for footings and stem walls, 地下设施.
4月, work begins to prepare the lower field area, and the concrete block wall on the west side of the school site will be complete.
阅读邻里动态 from Lydig Construction, which is distributed to homes nearby.
当前的设计
网站计划
Here is the presentation from the meeting.
Questions and Answers from Community Meetings
Below you will find the questions/comments and answers from community meetings
School Design Advisory Team (SDAT)
在设计过程的早期, representatives from the school community come together to form a school’s SDAT. SDATs typically include school and district staff, 父母, and community members. Students are sometimes included for all or part of the process. The project construction managers also take part. Learn more about the 约翰罗杰斯小学 SDAT.
更多的信息
网站的大小: 9.1 acre site is partially in the flood plain for 桑顿溪.
师: 经销商集团
General Contractor/Construction Management Firm (GC/CM): Lydig施工
项目预算: $91.5M
资金来源: Funded by the Building Excellence V (BEX V) Capital Levy, approved by Seattle voters in 2019.
联系
For questions or comments about this project, please use our online Let’s Talk form.
项目经理: 阿曼达Fulford) asfulford1@unpopperuno.com, 206-252-0697